(SOURCE: La Gazzetta dello Sport Milano and Lombardia, 25 August edition)
A quick update on the San Siro renovation work, as detailed in the Milano and Lombardia edition of today’s La Gazzetta.
On Monday 2 September (the second round of Serie A will be complete, and it will be the international break), work will begin on removing the gaps and barriers that separate the pitch from the stands. The orange stand will be the first to have this work complete, and it will take around 15 days to complete.
Next year they will then do the same for the green and blue stands, which are the two sections behind each goal.